Are pre-lien notices for a Kentucky Mechanics Lien Claim required?
In some instances. All potential Kentucky mechanics lien claimants must serve a formal notice on the owner by regular mail within 7 days of the filing of the Kentucky construction lien statement. Additionally, lienors without written contracts with the owner must notify the owner in writing within 75 days of last work for contracts of $1,000 or less and within 120 days for contracts exceeding $1,000.00. When owner-occupied single or double family dwellings are involved, the notice to the owner must be within 45 days.