Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Are pre-lien notices for an Illinois Mechanics Lien Claim required?

0
Posted

Are pre-lien notices for an Illinois Mechanics Lien Claim required?

0

Yes. Within 60 days from beginning work on a single family, owner occupied residence, subcontractors and suppliers who do not have a contract with the owner must provide notice to the owner that they are supplying labor or materials. On all projects, within 90 days of the completion of the work, subcontractors and suppliers who do not have a contract with the owner must provide notice to the owner and the mortgagee.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.