Are the apparent low bidders subcontractors exceeding 5% required to submit their Escrow Bid Documents two business days after the bid opening?
Yes. See Contract Documents and Section 01005, Part 1.05. 2008-06-19 Please clarify the difference between “temporary exclusive access” and “temporary nonexclusive access”. The term “temporary exclusive access” refers to temporary access to an area for the exclusive use of the MTPT Contractor. The “temporary nonexclusive access” refers to temporary access to an area by the MTPT Contractor that is being used concurrently by the FRS II contractor. 2008-06-19 Regarding the completion times, does “complete construction of the Inlet/Outlet Shaft” include only shaft excavation and support or does it include installation of the steel piping and elbow, concrete backfill and contact grouting? The construction of the shaft includes the excavation, support, installation of the steel piping and concrete backfill. If the Contractor chooses to install the elbow from the shaft, the elbow installation, backfill and contact grouting must also be performed before the completion time specified for the ‘c
Related Questions
- Are the apparent low bidders subcontractors exceeding 5% required to submit their Escrow Bid Documents two business days after the bid opening?
- Up to how many apparent low bidders will be required to submit items due within two business days after bid opening?
- What is in place to ensure that a contractor does not submit a low bid and then raise the price after they win?