Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Can I pour a concrete slab in the building after construction is completed?

0
Posted

Can I pour a concrete slab in the building after construction is completed?

0

A. YES. If your concrete contractor requires additional access other then the main door, some wall metal can be left off and installed by the customer after the concrete is poured. The bottom plate of all NAB buildings are 2 x 6 ACQ treated and can be used as a form for your concrete pour.