Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

Explain the cut-off dates for deciding whether or not a VE study must be performed on an applicable project?

0
Posted

Explain the cut-off dates for deciding whether or not a VE study must be performed on an applicable project?

0

The NHS law was passed in November 1995 and FHWA’s VE regulation became effective on March 17, 1997. If a project’s design was completed before March 17, 1997, no VE study is required.