How far below the Chattahoochee River will the pipeline be buried?
All engineering design and installation of this crossing will comply with permit requirements. The Army Corps of Engineers typically requires a drilling depth of at least 25 feet below the river’s bed. However, the pipeline will probably be installed deeper than required by the Corps of Engineers in order to provide additional separation between the bottom of the river and the path of the pipeline bore.