Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How is the work-scope of a CMAQ project modified?

cmaq modified project
0
Posted

How is the work-scope of a CMAQ project modified?

0

Prior to contract/MOA: The sponsor must submit a formal request to the GDOT project manager detailing the changes to be made and the reason for those changes. Any funding difference is the responsibility of the sponsor, and all changes must abide by the goals originally defined in the application and through the CMAQ guidelines. If the changes are approved, the sponsor will be notified by the project manager. Under contract: Any changes to the work-scope or funding amounts must be approved by GDOT. Significant changes require an amendment or supplement to the existing contract. The amendment will detail the changes to be made and be signed by both GDOT and the project sponsor.

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.