Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How is “Work” calculated in Tasks?

calculated tasks
0
10 Posted

How is “Work” calculated in Tasks?

0
10

The field named Work in Task Information view is calculated using this equitation: Work= Duration x Units The task properties are defined as follows: Work= Number of hours of planned work Duration= Difference between the task start and end dates Units= The percentage of a resource’s time spent working on the task (Resource Allocation Units- our resources are 100% allocated, but more than one resource may be assigned to a task)

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.