Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long should cement:sand screed be left before tiling?

cement Left Sand screed tiling
0
Posted

How long should cement:sand screed be left before tiling?

0

3 weeks for Portland cement (including 7 days cure + 2 weeks continuous drying out in air) or 24 hours for screeds incorporating BAL Quickset Cement. If not possible to allow Portland cement:sand screed to dry for 3 weeks, allow min. 24 hours for drying, then tile using BAL Green Screed Adhesive.