Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How soon after shooting a pool shell can formwork be removed? How soon can tiling begin?

0
Posted

How soon after shooting a pool shell can formwork be removed? How soon can tiling begin?

0

Vertical formwork can generally be removed the day following the shotcrete installation. If the formwork is supporting a load like a soffit form, the form should not be removed until the shotcrete has attained full strength such that it can support the weight of the member. Your question regarding the installation of the tile should be directed to a professional who installs tile. (back to top) Question 103: We have an approximately 9500 ft2 (882.6 m2) pool that was built and finished in midsummer. Four weeks later, the pool has developed “spider web” cracking in the bottom. We need to have a compressive strength test done. Our crew is on site now and is going to pull a 4 in. (101.6 mm) core sample for testing. I need to know what procedure to follow and where to send the sample for testing. Answer: Consult with a local engineering firm that is qualified to develop a coring plan, obtain cores, and perform testing in accordance with ASTM C42/C42M or ASTM C1604/C1604M. Please refer to AS

0

Vertical formwork can generally be removed the day following the shotcrete installation. If the formwork is supporting a load like a soffit form, the form should not be removed until the shotcrete has attained full strength such that it can support the weight of the member. Your question regarding the installation of the tile should be directed to a professional who installs tile. (back to top) Question 103: We have an approximately 9500 ft2 (882.6 m2) pool that was built and finished in midsummer. Four weeks later, the pool has developed “spider web” cracking in the bottom. We need to have a compressive strength test done. Our crew is on site now and is going to pull a 4 in. (101.6 mm) core sample for testing. I need to know what procedure to follow and where to send the sample for testing. Answer: Consult with a local engineering firm that is qualified to develop a coring plan, obtain cores, and perform testing in accordance with ASTM C42/C42M or ASTM C1604/C1604M. Please refer to AS

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.