Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

In a cost plus fixed fee contract, can one negotiate a maximum overhead rate even though the overhead rates are subject to audit?

0
10 Posted

In a cost plus fixed fee contract, can one negotiate a maximum overhead rate even though the overhead rates are subject to audit?

0
10

A. You can negotiate an advance agreement with the contractor establishing a ceiling overhead rate for any given fiscal/calendar year and state that the final overhead rate payable on the contract will be established by a final contract audit, except that in no event will the final rate payable exceed the ceiling rate(s) stipulated in the contract. In the event that the audited overhead rates are less than the rates the contractor billed you during the course of the contract, the lesser (audited) rates will be the final rates paid. (Revised: October, 2010) Q.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.