Is an Owner’s Project Manager (OPM) required on every school construction project that moves forward in the MSBA Process?
A. Pursuant to state law, if the estimated construction cost is estimated to be $1.5 million or greater an OPM is required. For school construction or renovation projects seeking funding from the MSBA, the MSBA must approve the OPM. In some instances the MSBA will require an OPM for projects under the $1.5 million threshold.