Is the compressive strength of the CIDH pile concrete 3,500 psi?
See “General Notes” (sheet 2/33) where fc of all reinforced concrete is required to be 3600 psi. Also see Section 10-1.25B(1), second paragraph, page SP-88 of the Special Provisions, where the minimum amount of cementitious materials is specified for concrete deposited under slurry. 9. Question: Section 10-1.25, “Piling,”–Will encounters with existing H-piles that are out of alignment be paid at force account for any & all work to remove the conflicting portion? Answer: Extra work at force account is the most probable method of payment for removing H-piles that infringe on the planned pile construction. 10. Question: Section 10-1.25, “Piling,”–Under the difficult pile installation section, hazardous and contaminated material is mentioned. Please provide additional information as to where and what should be expected. Answer: No hazardous or contaminated material was found; its presence is not unexpected. 11. Question: Can a vibratory hammer be used to install and remove temporary casi