Is the DG Capacity 11 kVA or less?
Yes No 7. Is the Short Circuit Current Contribution screen met? No Yes 8. Is the Line Configuration screen met? No Yes Yes No INITIAL REVIEW PROCESS DETAILS: 1. Does the DG qualify for net metering? If YES, go to a separate process for net-metered DG (per P.U. Code Sec. 2827) If NO, continue to next screen. Significance: 1. Net-metered systems are covered by state legislation (refer to Section 2827 of the Public Utilities Code). Criteria to Qualify for Net-Metering: 1. DG facility must comply with PUC Code Section 2827 2. Is the Point of Common Coupling (PCC) on a Networked Secondary System? If NO, continue to next screen. If YES, DG does not qualify for Simplified Interconnection. Perform supplemental review. Significance: 1. Special considerations must be given to DG on networked secondary distribution systems because of the design and operational aspects of network protectors. There are no such considerations for radial distribution systems. 3. Will power be exported across the PCC?