Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

The cost always shows as 0.0 in the Plan view even after assigning the resources. How can I change this value?

0
Posted

The cost always shows as 0.0 in the Plan view even after assigning the resources. How can I change this value?

0

The resources need to be assigned a cost first. To do so, go to the Resource view. Double-click on the task to get the Resource Details dialog. The cost pertaining to the resource can be filled in here. Then the cost will be reflected in the Plan view if these resources are assigned to the tasks.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.