We can only find about 1,600 cy of Roadway Excavation under the pavement removal. Where is the rest of the Roadway Excavation?
The Roadway Excavation Item Includes all material removed under the pavement removal at the bridge ends. Additionally, this item will be used for the asphalt and DGA material that will be removed for the strengthening of the existing asphalt shoulder pavement for traffic control at the bridge ends.