What are lead time and lag time, and why are they important in scheduling?
Lead time is an overlap of two activities in a schedule, so the successor activity starts before the predecessor activity finishes. Lag time represents a delay between the finish of the predecessor activity and the start of the successor activity. While the original schedule may be perfectly operational with these types of relationships in place, using these shortcuts leads to problems when the schedule is updated for actual progress.