What are the priorities for spending the Seismic Safety Bond funds?
Based on the findings and recommendations made by ATI, the District established the following priorities for establishing the timing and order of the construction under the Seismic Safety Bond Program: Priority #1 Havens Main Building & Annex PHS 30′s Building PHS Student Center Priority #2 Beach 1930′s Buildings Wildwood 1930′s Buildings Havens Ellen Driscoll Auditorium PHS Alan Harvey Theatre Priority #3 PMS Main Building PHS Building & Campus Access Maintenance Facilities Back to top ↑