What are they clearing for behind Blockbuster, Taco Bell, and Old Cub Foods?
Nothing. They are using this area to accumulate the debris from road construction including landscaping. At some point, they will bring in a chipper and grind up all the debris for mulch to recycle. Is there a time table for the Davis Road Connector to be completed? Not yet. The preliminary concept meeting with GDOT was positive, but there are no final plans yet. Once final plans are completed, will take months, then we have to go through an environmental review process that may take up to 18 months, then and only then, could we begin acquisition of ROW (right of way), and then after that, schedule construction. I would guess at a minimum two to three years. If possible to accelerate, we’d like to do that, but so far, doesn’t look like it. Can you give me a general statement about the median project? The first phase is from where to where? When is this first phase expected to be completed? Lanes closing when? Preparations for actual road construction are well underway. The clearing cre