What is the sequencing of the deconstruction plan and what is the current timeline for activities?
Top ^ The goal is to complete the work in 11 sequences beginning with the top 4 floors and continuing downward in 4 floor sections towards the basement. The sequencing and the schedule of these activities will be finalized after approval of the plan. Development of the two-phased Deconstruction Plan was based on the results of the Initial Building Characterization Study Report that was released for public review and comment in September 2004. The information provided in the current Deconstruction Plan addresses the Phase I work only. A Phase II plan will be developed and presented prior to the start of that work. The draft Phase I plan is available for public viewing on LMDC’s website at www.RenewNYC.com. Please note that the 130 Liberty Street Draft Phase I Deconstruction Plan is currently under review by the regulators and subject to change.