What is the submission sequence for project documentation?
• The submission sequence of documentation for a typical project is as follows: Planning/Regulatory Compliance Documentation Submittals • MAG 208 Certification Documentation – Submitted with an Approval To Construct or Approval Of Proposed Plan application. • Planning Documentation (Master Plan Report, Capacity Study, etc.) – Submitted with an Approval To Construct or Approval Of Proposed Plan application. • Regulatory Compliance Documentation – Submitted with an Approval To Construct or Approval Of Proposed Plan application as dictated by the terms stated within a Consent Decree or other agreement. Design Documentation Submittals • Engineering Design Report, Calculations and Design Data – Submitted with an Approval To Construct application. • Design Drawings – A set of preliminary design drawings are submitted with an Approval To Construct application. The drawings may be submitted for review and approval as 90% or 95% complete drawings depending on the size and complexity of the proj