What is the timetable for implementation of the VTA Express Lanes Project?

0
Posted

What is the timetable for implementation of the VTA Express Lanes Project?

0

VTA has completed a feasibility study and begun the preliminary design for the project which will be submitted for VTA Board approval in December 2008. Pending Board approval, the final design will begin in 2009, with anticipated operation to begin first on SR 85 in 2012 and on U.S. 101.between 2013 to 2015.