What is the timetable for the building process for the new ICC premises?
• Selection of the architect: 2009 • Start design phase: the design phase started in March 2010 and is due to be completed the end of 2011 • Tendering and contracting: second half of 2011 and beginning 2012 • Construction: start mid 2012 • Construction: completion September 2015 • Building in use: December 2015