Why aren’t there two shifts being used during the summer months to speed up the completion of the Centre?
A. This strategy is being constantly evaluated and used for trade packages on a case-by-case basis. We foresee cases where we will be able to use multiple shifts. The use of additional shifts is limited to work that does not require a continuous supply of materials such as concrete and gravel that are only available during normal working hours. The use of additional shifts often has a cost premium which has to be weighed against any time advantage.