How long will it take to meet the requirements for participation in the ATR Pilot program?
There are several requirements to be met prior to becoming an active resource in the ISO-NE Regulation market. Many of the requirements can be accomplished in conjunction with one another: • NEPOOL Membership – Allow 2 to 3 months • Interconnection: • Must have signed agreement with local Transmission Operator – Allow 3 to 4 months • Submission of I.3.9 Proposed Plan for generator interconnection or Less than 5 MWs Generator Notification Form.