Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How will the pipeline be installed in Trails End Road?

installed pipeline
0
Posted

How will the pipeline be installed in Trails End Road?

0

The 78-inch (6 ½ foot) pipeline will be tunneled under the Sandy Creek Arm of Lake Travis to the south end of the right-of-way of Trails End Road. Open cut and cover methods will be used within the right-of-way of Trails End Road to its intersection with RM 1431. This will typically require excavation of a trench with a width of approximately 10 feet and a depth of 14 feet. After the pipe is installed, the trench will be filled and the ground will be compacted back to its original elevation.

Related Questions

What is your question?

*Sadly, we had to bring back ads too. Hopefully more targeted.

Experts123