The Inlet Shaft Mitered Elbow, per Drawing T-20, shows that only one field weld is required. Is it correct that it is to be delivered at the job site as two pieces?
No, the Contractor shall determine how many field welds are required. 2008-06-19 For the field butt weld required on the Inlet Shaft Mitered Elbow on Drawing T-20, we believe the backing bar as shown on Detail 1 of Drawing T-19 will not work when placed at an angle point like in this case. Please review the design and advise. See Addendum 4. 2008-06-19 Section 01311, Part 1.06, Paragraph A states Constructions Schedules shall be prepared with the latest version of Primavera Project Management for Windows. Section 01590, Part 1.09, Paragraph F states the requirement of having Primavera Project Planner 3.1 at the field office. Primavera Project Planner 3.1 is not the latest version. What are we supposed to use? See Addendum 4. The Contractor shall use Primavera Project Manager 5.0 or newer.