What does building commissioning cost?
The cost of building commissioning depends upon the complexity of the building systems and the scope of the services being requested. Owners typically budget M/E/P building commissioning at 0.5% to 1.0% of the overall construction cost. Some choose instead to budget commissioning costs at 3% to 4% of mechanical construction cost and 1.0% to 2.0% of electrical construction cost. The value of building ommissioning far outweighs its financial cost. Case studies on building commissioning projects have shown that building commissioning generally pays for itself in 1 to 2 years through increased energy efficiency (reduced utility bills) and decreased operating costs (reduced maintenance and troubleshooting costs).