What is the status of the current SRTS infrastructure program?
A. As of 9-27-10, the report is HERE . Report is sorting by Program Year (PGM YR) along with the PPS # (PGM NO). The “Y” indicates it is programmed with OP&P in PPS. (normally not entered until Stage 6) The CNTY is the Federal County Code The TYPE is an Agency Type – 1 = County, 2 = Township and 3 = City The NAME is the Local Agency The RTE is the Route Name The SECTION is our local section # The PROJECT is the Federal Project # The STG is the “status” of the project – (Typically projects go from Stage 1 to Stage 6) Stage 7 = Project is closed, a Final Voucher has been filed Stage 6 = Project has been authorized with the Feds Stage 5 – 3 = are not used Stage 2 = a Program revision has been sent for changes to the Annual Program Stage 1 = Initial entry of the Project. The LET DATE is the letting date TOTAL PROJECT COST FED FUND TYPE is our federal fund key – SRSP = Phase 1 Engineering SRS2 = Phase 2 Engineering SRS = Construction SRSC = Construction Engineering SRSR = Land Acquisition T