Important Notice: Our web hosting provider recently started charging us for additional visits, which was unexpected. In response, we're seeking donations. Depending on the situation, we may explore different monetization options for our Community and Expert Contributors. It's crucial to provide more returns for their expertise and offer more Expert Validated Answers or AI Validated Answers. Learn more about our hosting issue here.

How long does it take to process the Domestic Wastewater Collection / Transmission System Construction (Sewer Extension) Permit?

0
Posted

How long does it take to process the Domestic Wastewater Collection / Transmission System Construction (Sewer Extension) Permit?

0

As provided by FDEP regulations and the Specific Operating Agreement (SOA) existing between DERM and the FDEP, a response from DERM is required within 30 days of submittal.